MyConstructionCalc

Rebar spacing: maximum spacing versus what gets tied on site

The right number of bars in the bay does not mean every gap is legal.

Setting out a mat

When a drawing says T16 at 200 mm centres, this is what happens on the deck:

  1. Establish the first bar. Measure from the formwork edge or control line, allowing for cover plus half the bar diameter.
  2. Mark the increments. Run a tape along the formwork or blinding and mark 200 mm steps with chalk, paint or a keel crayon.
  3. Lay and align. Bars go down on the marks; runner bars or snapped chalk lines guide top mats and wall grids.
  4. Tie. Usually 1.6 mm soft annealed wire, snap tie, figure-of-eight or saddle tie depending on where it is.

Checking it

Three different meanings of "spacing"

The gap between the second and third is where the problem lives. Layout errors accumulate along a long bay and get absorbed into the last space. A run that ends with one 260 mm gap has the correct total bar count and a location that does not comply, because that gap is a strip of effectively unreinforced concrete.

The opposite error also matters. Bars tied too close together — less than about 20 to 25 mm clear, or under the coarse aggregate size plus a margin — stop aggregate passing through. Concrete cannot flow, and you get honeycombing and voids under the mat, plus a bond that never fully forms because paste has not encapsulated the bar.

Cover

Cover is controlled with hardware, not with care:

Before the pour, measure from the outer face of the steel, including links, to the shutter face or blinding. Check spacer frequency — around one to one and a half blocks per square metre is typical — and walk the top mat to confirm the chairs do not fold under a worker's weight. After the pour, a cover meter will scan the hardened concrete and confirm what was actually achieved.

Tolerances, and who sets them

The structural engineer of record decides. A site engineer or QA/QC inspector cannot grant a relaxation beyond the code or the specification without written approval from the consultant's structural engineer, however reasonable it looks on the day.

What actually comes up at pre-pour inspection

None of these are exotic. They are what a careful walk of the deck with a tape and a torch finds, an hour before the concrete is due.

This guide describes general practice and typical figures. Your project specification, job mix formula and laboratory results govern the actual values on your job. Nothing here is a design or a substitute for the engineer of record.